Alaska retainage law: no cap, 8 working days to pay subs (2026)
By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer
Alaska's construction payment article, AS 36.90.200 to 36.90.290, covers public work and sets no retainage percentage. The state or political subdivision pays the prime contractor interest on retainage from the date a pay request is approved until payment, and the prime pays each subcontractor its retainage within eight working days after receiving final payment. Private work has no statutory rule.
Private work
Alaska · Private workVerified 2026-09-29
Retainage cap
No statewide statute
Alaska's construction payment article, AS 36.90.200 to 36.90.290, applies to public construction and public works contracts of the state and its political subdivisions. It sets no retainage rule for private work, so a private contract governs.
Deadline
No statewide statute
Statute
No statewide statute
Public work
Alaska · Public workVerified 2026-09-29
Retainage cap
AS 36.90.200 to 36.90.290 set no maximum retainage percentage. They require the state or political subdivision to pay the prime contractor interest on retainage, including warranty retainage, and require every public subcontract to carry clauses that pass retainage down within eight working days. A political subdivision with a population of 500 or less is exempt from the interest on retainage, and a contract provision that waives a provision of the article is void (AS 36.90.270).
Deadline
8 days
Final payment to the prime contractor by the state or political subdivision (or the end of the AS 36.25.020(b) notice period, if later). The eight working days are the prime contractor's deadline for paying each subcontractor its retainage; the article sets no date for the owner's own release of retainage.
The state or a political subdivision of the state shall pay to the prime contractor interest on retainage, including warranty retainage, on a contract for public construction or public works at an interest rate that is equal to the amount set out in AS 45.45.010 (a). Interest on retainage accrues from the date of approval of a pay request until the date of payment to the contractor.
Alaska Stat. § 36.90.250 (retainage); § 36.90.210 (required contractual terms). · Official text · retrieved 2026-09-29
Who this applies to
Alaska's rules sit in one article of Title 36, AS 36.90.200 to 36.90.290, and that article is written for public construction and public works contracts of the state and its political subdivisions [2]. Under AS 36.90.265, it applies to a political subdivision's contract if the subdivision has entered into a written contract with the state for the state to provide funds for the project [2]. Two relationships are covered: the public owner and its prime contractor, and the prime contractor and its subcontractors [1].
On a private job, no statute caps retainage or sets a release date, so the contract governs [2].
What the rule says
Alaska does not limit how much retainage a public owner may hold. The article works on the cost of holding it and on how quickly it moves down the chain.
Interest from the owner. Under AS 36.90.250(a), the state or political subdivision pays the prime contractor interest on retainage, warranty retainage included, at the rate set in AS 45.45.010(a) [1]. Interest runs from the day a pay request is approved until the day the contractor is paid [1]. A political subdivision with a population of 500 or less is exempt from this interest [1].
Pass-down to subcontractors. Every public subcontract must carry clauses that require the prime to pay the subcontractor all retainage due within eight working days [1] after the prime receives final payment from the public owner, or after the notice period under AS 36.25.020(b) expires, whichever is later [1]. The same required clauses provide interest on retainage withheld from subcontractors and their suppliers at the same statutory rate [1].
The eight working days are the prime contractor's deadline. No section of the article names a separate deadline for the public owner's release of retainage to the prime, and the late-payment interest in AS 36.90.200 does not apply to retainage [1].
How to comply
Prime contractors on public work. Read the pay-request approval dates in the project record; interest on the retainage the owner holds accrues from each one [1]. If the owner is a political subdivision with a population of 500 or less, that interest does not apply [1].
Subcontract terms. Check that each subcontract on a public job contains the pass-down clause and the interest clause AS 36.90.210 requires [1].
Subcontractors. The clock starts when the prime receives final payment from the owner, or when the AS 36.25.020(b) notice period ends if that is later; from there the prime has eight working days [1]. Working days, not calendar days, are the unit [1].
Waivers. A contract provision that waives a provision of the article is void under AS 36.90.270 [2].
The article's full text, linked in the Sources below, and the contract documents settle how these rules fall on a particular project; this page is a summary of the statute, not a reading of any one contract.
Related
Retainage calculator: put a dollar figure on the retainage held on each pay request.
Retainage laws by state: Alaska's interest-and-pass-down approach beside other states' caps.
: 1 more jurisdiction verified and published, 47 of 51 in all.
: California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
: Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
: Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
: Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
: Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
: Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
: Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
: Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
: District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
: Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
: Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
: Page updated.
: Page published.
: 10 more jurisdictions verified and published, 46 of 51 in all.
: Dataset first published with 36 of 51 jurisdictions verified.