Retainage · Idaho

Idaho retainage law: 5% cap on public and private work (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Idaho caps retainage at 5% on both sides. On public works where the public body requires a bond above 50% of the contract, § 54-1926(3) allows no more than 5% of the amount payable, released 30 days after a portion is accepted. On private work, § 29-115 caps retention at 5% of each payment and of the contract price, released within 35 days of final completion; owner-occupied homes of 1 to 4 units are excluded.

Private work

Idaho · Private workVerified 2026-09-29
Retainage cap
5%
Idaho Code § 29-115(2): on any contract relating to the construction of a private work of improvement, retention withheld by the owner from the original contractor, or by the original contractor from any subcontractor, shall not exceed 5% of any payment, and total retention shall not exceed 5% of the contract price. The 5% maximum does not apply if the original contractor or subcontractor fails to provide a performance bond from a surety acceptable to the owner or original contractor when asked for one, or to a contract for residential real property of one to four units occupied or to be occupied by the owner. The section applies to contracts between owners and original contractors entered into on or after July 1, 1990 (§ 29-115(1)), and a party may not require another to waive it (§ 29-115(7)).
Deadline
35 days
Final completion of the work of improvement: the owner releases retention within 35 days, and may withhold up to 150% of the estimated value of an issue in dispute and condition the final release on lien waivers (§ 29-115(3)). The original contractor pays each subcontractor its share within 10 days of receiving retention, less up to 150% of the value of a bona fide dispute (§ 29-115(4)-(5)).
What the statute says
In any contract relating to the construction of any private work of improvement, the retention proceeds withheld by the owner from the original contractor or by the original contractor from any subcontractor from any payment shall not exceed five percent (5%) of the payment and in no event shall the total retention withheld exceed five percent (5%) of the contract price.
Idaho Code § 29-115. · Official text · retrieved 2026-10-17

Public work

Idaho · Public workVerified 2026-09-29
Retainage cap
5%
Idaho Code § 54-1926(3): a public body that requires a performance or payment bond above 50% of the contract amount may not withhold more than 5% of the total amount payable as retainage, and the same 5% limit applies to what a contractor withholds from a subcontractor. Public works contracts of $50,000 or more require performance and payment bonds of at least 85% of the contract amount (§ 54-1926(1)-(2)).
Deadline
30 days
Acceptance of the completed portion of the project by the public body and the contractor; a contractor must pay a subcontractor's retainage within 30 days after the subcontract is completed.
What the statute says
Public bodies requiring a performance bond or payment bond in excess of fifty percent (50%) of the total contract amount shall not be authorized to withhold from the contractor or subcontractor any amount exceeding five percent (5%) of the total amount payable as retainage.
Idaho Code § 54-1926(3). · Archived copy of the official text, captured 2026-06-16

Who this applies to

The Idaho rule is part of the public works bonding statute, Idaho Code § 54-1926 [2]. Its retainage limit applies where a public body requires a performance bond or payment bond in excess of 50% [2] of the total contract amount. The same section requires performance and payment bonds of at least 85% [2] of the contract amount on public works contracts of $50,000 [2] or more.

The limit protects two tiers: the contractor, against the public body, and the subcontractor, against the contractor [2].

Private work has a statute of its own, Idaho Code § 29-115, covering contracts between owners and original contractors on a private work of improvement entered into on or after July 1, 1990 [3]. It reaches the original contractor's retention from its subcontractors too, and no party may require another to waive it [3].

What the rule says

The ceiling. A public body that requires a bond above the 50% [2] threshold may not withhold from the contractor or subcontractor more than 5% [2] of the total amount payable as retainage. A contractor is held to the same 5% [2] in what it withholds from a subcontractor.

Release in stages. The section does not make the contractor wait for the end of the job. Retainage for any portion of the project that the public body and the contractors accept as complete is released within 30 days [2] after that acceptance. Down the chain, a contractor pays a subcontractor's retainage within 30 days [2] after the subcontract is completed.

Private work. Retention withheld by the owner from the original contractor, or by the original contractor from a subcontractor, may not exceed 5% of any payment or 5% of the contract price in total [3]. The 5% maximum does not apply if the contractor or subcontractor fails to provide a performance bond when asked for one, or to work on residential property of one to four units occupied or to be occupied by the owner [3]. Within 35 days of substantial completion, retention comes down to the lesser of 150% of the estimated value of the work left or the amount then held [3]. Within 35 days of final completion it is released, though the owner may keep up to 150% of the estimated value of an issue in dispute and may require lien waivers first [3]. The original contractor then has 10 days to pay each subcontractor its share [3].

Interest. A companion statute, Idaho Code § 67-2302, makes interest run on retained amounts owed by the state or a tax-supported taxing district starting 30 calendar days [1] after the contractor completes the work, unless the contract provides otherwise [1].

How to comply

  1. Confirm whether the contract requires a performance or payment bond above 50% [2] of the contract amount; the 5% [2] ceiling depends on it.
  2. Compare the retainage clause in the prime contract, and in each subcontract, with 5% [2] of the total amount payable.
  3. When a portion of the work is accepted as complete, date the acceptance. The 30-day [2] release period runs from that date, for that portion.
  4. A subcontractor can measure its own 30 days [2] from the completion of its subcontract.
  5. Read the payment terms for any clause on interest; § 67-2302 lets the contract provide otherwise [1].
  6. On a private job, compare the retention clause with 5% [3] of each payment and of the contract price, date substantial and final completion, and count 35 days [3] from each.

What this page gives is the rule as the statute states it. Whether it reaches a particular contract is a question for the contract, the sections linked below and a lawyer.

What changed recently

Section 54-1926 was added in 1965, ch. 28, and last amended in 2017, ch. 197, sec. 3 [2]. Section 29-115, the private rule, was added in 1990 and amended in 1998 and in 2025, when chapter 34 added a subsection requiring Idaho law to govern private construction contracts in Idaho [3].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. Idaho Code § 67-2302, Idaho State Legislature (archived copy, captured 2026-01-18)
  2. Idaho Code § 54-1926 (performance and payment bonds; retainage on public works), Idaho State Legislature (archived copy, captured 2026-06-16)
  3. Idaho Code § 29-115, construction contracts (private works retention), Idaho Legislature (retrieved 2026-10-17)

Changelog

  1. : Page updated.
  2. : 1 more jurisdiction verified and published, 47 of 51 in all.
  3. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  4. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  5. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  6. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  7. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  8. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  9. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  10. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  11. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  12. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  13. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.