Who this applies to
The Idaho rule is part of the public works bonding statute, Idaho Code § 54-1926 [2]. Its retainage limit applies where a public body requires a performance bond or payment bond in excess of 50% [2] of the total contract amount. The same section requires performance and payment bonds of at least 85% [2] of the contract amount on public works contracts of $50,000 [2] or more.
The limit protects two tiers: the contractor, against the public body, and the subcontractor, against the contractor [2].
Private work has a statute of its own, Idaho Code § 29-115, covering contracts between owners and original contractors on a private work of improvement entered into on or after July 1, 1990 [3]. It reaches the original contractor's retention from its subcontractors too, and no party may require another to waive it [3].
What the rule says
The ceiling. A public body that requires a bond above the 50% [2] threshold may not withhold from the contractor or subcontractor more than 5% [2] of the total amount payable as retainage. A contractor is held to the same 5% [2] in what it withholds from a subcontractor.
Release in stages. The section does not make the contractor wait for the end of the job. Retainage for any portion of the project that the public body and the contractors accept as complete is released within 30 days [2] after that acceptance. Down the chain, a contractor pays a subcontractor's retainage within 30 days [2] after the subcontract is completed.
Private work. Retention withheld by the owner from the original contractor, or by the original contractor from a subcontractor, may not exceed 5% of any payment or 5% of the contract price in total [3]. The 5% maximum does not apply if the contractor or subcontractor fails to provide a performance bond when asked for one, or to work on residential property of one to four units occupied or to be occupied by the owner [3]. Within 35 days of substantial completion, retention comes down to the lesser of 150% of the estimated value of the work left or the amount then held [3]. Within 35 days of final completion it is released, though the owner may keep up to 150% of the estimated value of an issue in dispute and may require lien waivers first [3]. The original contractor then has 10 days to pay each subcontractor its share [3].
Interest. A companion statute, Idaho Code § 67-2302, makes interest run on retained amounts owed by the state or a tax-supported taxing district starting 30 calendar days [1] after the contractor completes the work, unless the contract provides otherwise [1].
How to comply
- Confirm whether the contract requires a performance or payment bond above 50% [2] of the contract amount; the 5% [2] ceiling depends on it.
- Compare the retainage clause in the prime contract, and in each subcontract, with 5% [2] of the total amount payable.
- When a portion of the work is accepted as complete, date the acceptance. The 30-day [2] release period runs from that date, for that portion.
- A subcontractor can measure its own 30 days [2] from the completion of its subcontract.
- Read the payment terms for any clause on interest; § 67-2302 lets the contract provide otherwise [1].
- On a private job, compare the retention clause with 5% [3] of each payment and of the contract price, date substantial and final completion, and count 35 days [3] from each.
What this page gives is the rule as the statute states it. Whether it reaches a particular contract is a question for the contract, the sections linked below and a lawyer.
What changed recently
Section 54-1926 was added in 1965, ch. 28, and last amended in 2017, ch. 197, sec. 3 [2]. Section 29-115, the private rule, was added in 1990 and amended in 1998 and in 2025, when chapter 34 added a subsection requiring Idaho law to govern private construction contracts in Idaho [3].