Retainage · South Dakota

South Dakota retainage law: no cap, 30-day final payment (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

South Dakota sets no percentage cap on retainage for public improvements. Under SDCL 5-18B-11, the purchasing agency keeps back from final payment the amount necessary to complete the improvement, and under SDCL 5-18B-14 final payment is due within 30 days after completion and acceptance. Interest is owed on retained amounts. The statutes cover public work only; private work is not addressed by them.

Private work

South Dakota · Private workVerified 2026-09-29
Retainage cap
Not in our verified record
Deadline
Not in our verified record
Statute
Not in our verified record

Public work

South Dakota · Public workVerified 2026-09-29
Retainage cap
No percentage cap in the statute. SDCL 5-18B-11 instead requires the purchasing agency to retain from final payment 'an amount necessary to complete the improvement.' Interest is owed on retained amounts and on final payment once the contractor has furnished all required records and reports and an inspection has occurred.
Deadline
30 days
Completion and acceptance of the public improvement by the purchasing agency: final payment of any sums due, including the amount retained from it, is due within thirty days after completion and acceptance. Interest on retained amounts runs from thirty days after the work is completed.
What the statute says
The contract may permit progress payments, but an amount necessary to complete the improvement shall be retained from the final payment until the contract is executed in full and the public improvement completed to the satisfaction and acceptance of the purchasing agency.
SDCL 5-18B-11 (retention from final payment; interest) and 5-18B-14 (final payment within thirty days). · Official text · retrieved 2026-09-29

Who this applies to

South Dakota's retainage provisions are in chapter 5-18B of its codified laws, which governs public improvements contracted by a purchasing agency [1]. The four sections that matter here, §§ 5-18B-11 to 5-18B-14, deal with progress payments, substitutes for retention, early occupancy and final payment [1] [2] [3] [4].

This page covers public work only. The chapter does not address private construction, so on a private job the contract and a lawyer answer the retainage question.

What the rule says

The statute does not use a percentage. A public improvement contract may permit progress payments, but an amount necessary to complete the improvement is retained from the final payment until the contract is executed in full and the improvement is completed to the purchasing agency's satisfaction and acceptance [1].

The deadline comes from § 5-18B-14 [4]. Final payment of any sums due to the contractor, the retained amount included, is made within 30 days [4] after completion and acceptance of the public improvement by the purchasing agency.

Holding money costs the agency interest. Once the contractor has furnished all required records and reports and a final inspection has been made, interest at not less than the Category E rate under SDCL 54-3-16 runs on retained amounts and on final payment from 30 days [1] after the work is completed, as shown by the architect's or engineer's letter of acceptance or by use and occupancy, until payment is tendered. For retainage on progress payments, the 30 days [1] count from the point the contractor has furnished the required records and reports and a progress inspection has occurred. Where federal participation is involved, interest can be delayed [1].

How to comply

  1. Read the retention clause. There is no statutory percentage to compare it with. The statute's measure is the amount necessary to complete the improvement, held from the final payment [1].
  2. Paper the job. Interest on retained amounts depends on the required records and reports being furnished and an inspection having occurred: a final inspection for the final payment, a progress inspection for retainage on progress payments [1].
  3. Substitute security. Section 5-18B-12 allows a bond or a deposit of securities in lieu of retention, where the contract permits it [2].
  4. Early occupancy. If the agency occupies the improvement before completion, § 5-18B-13 calls for payment of all but double the estimated cost to complete, or 1% [3] of the contract price, with a minimum of $300 [3].
  5. Final payment. Date completion and acceptance; the 30 days [4] start there.

What this page does is describe the four sections. Whether and how they apply to a given contract is for the statutes in the Sources below, the contract and a lawyer.

What changed recently

The source notes for §§ 5-18B-11 and 5-18B-12 cite SL 2010, ch 31, Secs. 50 and 51 [1] [2].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. SDCL 5-18B-11 (Progress payments; retention of funds from final payment; interest), South Dakota Legislature (retrieved 2026-09-29)
  2. SDCL 5-18B-12 (Bond or deposit of securities in lieu of retention), South Dakota Legislature (retrieved 2026-09-29)
  3. SDCL 5-18B-13 (Occupancy before completion and acceptance), South Dakota Legislature (retrieved 2026-09-29)
  4. SDCL 5-18B-14 (Project superintendent; installment payments; final payment), South Dakota Legislature (retrieved 2026-09-29)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page updated.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.